Government of Karnataka attaches much importance for Budgetary Allocations for Infrastructure Sector, especially for improving Air, Rail and Marine connectivity. Budgetary provisions made in the last Eight years is given below for information :

Year
Budgetary Provision
2002 - 2003
Rs. 178.00  Crore
2003 - 2004
Rs.167.60  Crore
2004 - 2005
Rs.137.77  Crore
2005 - 2006
Rs. 207.38  Crore
2006 - 2007 (Revised estimate)
Rs. 383.07  Crore
2007 - 2008
Rs. 422.13  Crore
2008 - 2009
Rs. 481.07  Crore

2009 - 2010

Rs. 425.14  Crore

Budget Allocation: 2010 - 11

For the year 2010 - 11 the department has been provided with the following budgetary allocations with a increment of 62% compared to the previous year:

(Rupees in Lakhs)

Sl.   No.

Head of Account & Name of the Scheme

RE 2009-10

BE 2010-11

1

2

3

4

Airports Infrastructure:-

1

5465-01-190-1-04-240 (Plan) - BIAP-Assistance for Re-payment of HUDCO Loans Debt Servicing

2599.00 2599.00

2a

5465-01-190-1-05-211 (Plan)        Development of Minor Airports

4000.00

4000.00

2b

5465-01-190-1-05-133 - Special Development Plan

6000.00

6000.00
3 5465-01-190-2-01 Investment in BIAL through KSIIDC 1500.00 1500.00
4 5465-01-190-2-02          BIAL-State Support to the project - -
5 5465-01-190-2-03 (Plan)             KSIIDC-BIAP cell-211 - Investments 25.00 25.00
6 5465-01-190-2-04-211 (Plan)            Providing power at the airport near BIAP site 1.00 1.00
7a 5465-01-190-2-05-211 Alternate Roads Investment 2000.00 1500.00
7b 5465-01-190-2-05-422 Special Component Plan 350.00
7c 5465-01-190-2-05-423 Trobal Sub Plan 150.00
8 5465-01-190-2-06 (Plan)        Land acquisition for Trumpet Interchange investments 200.00 200.00
9 5465-01-190-2-07-051 (Plan)          Development of 408 acres of Govt. land adjacent to BIAP 100.00 100.00
10 5465-01-190-2-11 (Plan)        Aviation Turbine Fuel - Tax Reimbursement Investment 36.00 36.00
11 5465-01-190-3-06-211 Rail link to New Airport 570.00 570.00

Total

17031.00

17031.00

Railways Infrastructure:-

12

5465-01-190-3-01 K-RIDE Investment

-

500.00

13

5465-01-190-3-02(Plan)               Hassan-Mangalore Guage conversion project - Investments.

900.00

900.00

14

5465-01-190-3-03 (Plan)         Sholapur - Gadag guage conversion project - Investments

2800.00

2800.00

15

5465-01-190-3-04 (Plan)         K-RIDE - RoB/RuB projects - Investments

3000.00

3000.00

16a

5465-01-190-3-05-211 New Cost Sharing project-Investments 10000.00 27250.00

16b

5465-01-190-3-05-133 Special Development Plan 4000.00

16c

5465-01-190-2-05 (P)          Alternate Roads Investment

2500.00

16d

5465-01-190-3-05-423 Tribal Sub Plan

1250.00
17 5465-01-190-3-07 - 211           Commuter Rail Services for Bangalore - Investments 100.00 100.00
18 5465-01-190-3-08 (Plan)         Cost sharing - Ramanagaram- Mysore railway doubling - Other expenditure 2500.00 2500.00
19 5465-01-190-3-09            Land for Railway Cargo Complex 1.00 1.00
20a 5465-01-190-3-10-133 Cost sharing - Bidar-Gulbarga new railway line - SDP 5000.00 4250.00

20b

5465-01-190-3-10-422 Special Component Plan

500.00

20c

5465-01-190-3-10-423 Tribal Sub Plan

250.00

21

5465-10-1901-11          Hubli Ankola Railway project.

1.00

1.00

Total

24302.00

49802.00

Others:-

22

5465-01-190-1-01-211 iDeCK - Investment

200.00

200.00

23

3451-00-090-1-06 (Plan) Infrastructure Preliminary Studies - 059 - Other Expenditure

881.00

797.00

24

3451-00-090-1-06 (Plan)  Infrastructure Preliminary Studies - 125-Modernisation & Capacity Building

100.00

100.00

25

5465-01-190-1-15 Karnataka Infrastructure Development Fund Capital Expenses

-

1000.00

Total (Railways)

1181.00

2097.00

GRAND TOTAL

42514.00 68930.00


 

Legal Disclaimer | Sitemap
Planning Commission | PPP in India | Dept. of Economic Affairs | BSNL | KSIIDC & IL&FS | PWD | KPTCL & ESCOM | UDD | KSRTC | BIAL | KIADB | BBMP | BDA | BWSSB | BMTC | iDeCK | HMRDC

Address: Principal Secretary, Infrastructure Development Department, Room 28, Vikasa Soudha, Bangalore-560001 INDIA
E-mail : prs-infra@karnataka.gov.in | Ph: 91-80-22035085 | Fax: 91-80-22280605

© 2009, Infrastrcture Development Department,Government of Karnataka. All rights reserved.
Design Consultants: Delsyst Technologies, Bangalore