Definitions
I Preamble
1.
Karnataka has been a forerunner of India’s economic growth.
Between 1996-97 and 2005-06, the Gross State Domestic Product (GSDP) at
constant prices grew at a compound rate of over 7% per annum, 16% higher than the
national average of over 6.0%. Had many of the infrastructure constraints not
existed, the growth rates could have been higher. 2.
Clearly recognizing the need to develop high quality
infrastructure as a means to achieve rapid economic growth, the Government of
Karnataka (GoK) had come out with an Infrastructure Policy in 1997. The
Infrastructure Policy of 1997 was aimed at expanding and upgrading
infrastructure to meet the growing needs of the industrial and agricultural
sectors, inviting private investment in infrastructure, and adopting a co-ordinated and integrated approach to infrastructure development. The policy
also had specific incentives and concessions for infrastructure projects.
However, with the efflux of time, there have been changes in the tax and stamp
duty regime, formulation of Government of India’s (GoI) policy on
Public-Private-Partnership (PPP) in infrastructure projects, and the concept of
the Viability Gap Fund (VGF). In line with these changes, GoK has now resolved
to formulate this new Infrastructure Policy. 3.
GoK has also set out several sectoral policies in the areas
of Power (1997, 2001), Ports (1997), Tourism (1997), Information Technology
(1997), and Roads (1998). GoK has also revised the Industrial Policy in 2006,
to take into account the developments and requirements in the industrial
development scenario. These policies have been evolved with a view to augment
and expedite infrastructure development through active private sector
participation. Despite these initiatives, there has not been any significant
increase in private investments, while public investment in project development
has been increasing steadily during the same period. Many of the infrastructure
constraints have remained, or even become more severe. 4.
GoK has sought to deal with some of these constraints by
implementing various programmes and projects departmentally and through GoK
agencies. These are being financed through various sources including budgetary
resources, grants and loans from GoI, and bilateral and multi-lateral agencies. 5.
GoK aims to achieve a high average growth rate in the coming
years, across all sectors, including infrastructure. These targets are expected
to be achieved by facilitating private sector investment and rapidly upgrading
technology. GoK recognises that high levels of economic and industrial growth
can be achieved only if infrastructure develops at a commensurate pace. GoK
also recognizes that the private sector can play a substantial role in
infrastructure development, and that given the right policies and frameworks,
adequate private investment can become available. GoK has already taken several
initiatives in this regard, envisaging significant investments in projects in
transportation (for airports, ports, railways and roads), tourism, power
generation, urban infrastructure, etc. II Objectives & Benefits of this Policy
6.
The main objective of GoK is to provide a fair and
transparent policy framework to help facilitate this process and encourage
Public-Private Partnership (PPP) in upgrading, expanding and developing of
infrastructure in the State. 7.
GoK, therefore, proposes to provide and facilitate an
increasing role for PPP ‑ both in creating new infrastructure assets, as
well as in managing assets already created. By this, GoK seeks to derive the
following benefits, which would deliver better value-for-money to the user: i.
Savings in costs due to innovative designs, timely project
implementation and higher efficiencies in operations ii.
Enhanced quality of services to users due to better
managerial practices & efficiencies iii.
Reduction in, and gradual elimination of, pricing constraints iv.
Enabling public funds to be earmarked for other commercially
non-viable but socially justifiable projects v.
Financial innovation and development of cost-effective
solutions vi.
Greater employment opportunities in the infrastructure sector 8.
PPP would be considered both in new Infrastructure Projects
and in managing existing Infrastructure Projects. The specific option to be
followed would be based on specific requirements, for which GoK may seek
recommendations from experts/ professional agencies. Where necessary, GoK may
also set up independent advisory group(s) to assist in the formulation of
sector strategies and selection of suitable implementation options. 9.
As far as possible, for all new investments in
infrastructure, the option of implementing the project through PPPs would be
considered first. GoK would directly invest in a project only after satisfying
itself that the same cannot be implemented through a PPP. Exceptions would be
projects in backward areas, or projects with high social relevance, but which
are prima-facie not financially viable. The
following models would be considered, inter-alia, for PPPs: ·
Project implementation by GoK/GoK Agency followed by a medium
or long-tenure O&M contract to a private operator ·
Project implementation by a Special Purpose Vehicle (SPV) set
up by GoK/GoK Agency followed by divestiture to a private operator after
stabilization of operations. ·
Project Implementation by a private developer/operator or
joint ventures with GoK under a licence/concession structure. 10.
GoK recognizes that for some projects it may be necessary for
Government of India or GoK to extend financial support by way of equity
participation, Viability Gap Fund[1], or other mechanisms in order to leverage the
desired levels of private finance. It is envisaged that the incentives/
financial support contemplated under this Policy are applicable: Ø For
infrastructure projects where, in the opinion of the Government, the project is
a public project set up for common use, where such infrastructure would
otherwise not be created; and Ø Only for
bridging the viability gap for Infrastructure Projects on a PPP basis. 11.
Given the experiences with the reform process in the last decade,
it is felt that a consistent approach needs to be followed in all
infrastructure sectors, so that the process of development is both uniform and
complementary. This Infrastructure Policy seeks to formulate the touchstone
principles that would constitute the broad framework for the development of
each infrastructure sector. 12.
In order to achieve this consistency, GoK would develop
medium and long term strategies and implementation plans for each of the
infrastructure sectors clearly setting out the role for PPP, which would allow
for the provision of adequate and reliable infrastructure services of high
quality at affordable prices to users. III Applicable Sectors
In all cases,
it is envisaged that the incentives/ financial support contemplated under this
Policy are applicable only if the conditions under Para 10 are met. The sectors/
areas in the ambit of the Policy would be modified as and when appropriate. IV Touchstone Principles
14.
The Infrastructure Policy has been developed around the
following main principles: ·
Efficient use of existing assets
and optimal allocation of additional resources ·
Payment for services ·
Equitable contractual structures ·
Transparent process of procurement ·
Fair regulatory framework ·
Enabling institutional frameworks ·
Sustainable incentives and
concessions A. Efficient Use of Assets and Allocation
of Resources
15.
GoK recognises that efficiency in allocation of resources can
be achieved by prioritisation of projects in an objective and unbiased manner.
To this end, GoK would first look at the option of better utilization of
existing assets before new investments are proposed. Priority would be accorded
to those projects where development of critical linkages provide significant
network or linkage benefits, as in the case of a transportation link
interfacing railways, roads and ports, or a power project in the vicinity of a
consumption centre. 16.
GoK would develop projects based on considerations of both
social need and economic viability, the focus being integrated infrastructure
development. GoK, however, recognises that “social” projects may not offer
sufficient commercial incentive for PPP. In such cases, Government would use
other compensation mechanisms like provision of VGF, or annuity payments. As an
alternative, GoK (or Government Agency) may implement such projects upfront and
eventually transfer management of services to a Private Sector Participant (PSP), where feasible. 17.
GoK would also develop objective criteria for rationalization
of investments for expanding, upgrading and/or development of Infrastructure.
Typically, project identification and prioritisation would be governed by the
following considerations: ·
Magnitude of gap between demand and supply for the
Infrastructure; ·
Focus on balanced regional development[2],
especially with regard to provision of basic Infrastructure; ·
Development of physical/ inter-sectoral linkages where
significant economic gains can be realized. 18.
Since GoK would actively promote PPP in Infrastructure
Projects, a larger share of investable public funds could be used for
identified social needs that may not otherwise be amenable to private finance
initiatives. In order to create a sustainable source of government funds for
long-term infrastructure financing, GoK would leverage internal and
extra-budgetary resources under various schemes such as the Infrastructure
Initiative Fund (IIF), ASIDE (Assistance to States for Infrastructure
Development for Exports), National Urban Renewal Mission (NURM), Viability Gap
Fund (VGF), and resources from iDeCK (PDF & PIF), KUIDFC, and bilateral and
multilateral agencies. B. Payment for Services
19.
GoK recognizes that in a system where pricing of services is
not economically sustainable, users would have no incentive to economize on
their use of resources, and service providers would have no incentive to become
more efficient. GoK believes that the inculcation of the “provider-charges” and
the “user-pays” principles is fundamental to the success of PPPs. To this end,
GoK would, where necessary and appropriate, consider levy of user charges
(tolls, fees, tariffs, cesses etc.) to meet the following objectives: ·
Create a stable and dedicated financial source for
construction/ redevelopment/ rehabilitation/ replacement of project assets and
their ongoing operations and maintenance in order to provide efficient,
sustainable and high quality services at affordable prices to users. ·
Manage demand ·
Encourage PPP ·
Cover costs of service provision ·
Recognising that economically weaker sections may require
certain subsidies in user charges, provide explicitly for such subsidies to the
project, to ensure that the project remains economically viable. 20.
The levy of user charges would be based on one or more of the
following criteria: ·
Savings to users ·
Willingness to Pay ·
Need for explicit subsidies ·
Uniformity between various projects ·
Cost Recovery ·
Debt service & Equity returns C. Contractual Structures
21.
GoK would set in place appropriate contractual arrangements
to give effect to the process of project implementation. GoK’s endeavour would
be to develop contractual frameworks that would allow for equitable allocation
of risks between the contracting parties, taking into account the legitimate
concerns of private investors. The attempt would be to allocate risks to the
party best suited to bear the risks. A matrix of typical project risks and risk
mitigation measures is set out in Schedule I. 22.
Existing Assets: The
contractual/ implementation structures used would include the following: ·
Management of the whole or part of the assets by private
operators through -
Operations and Maintenance (O&M) contracts for
pre-determined periods -
Lease of assets -
Rehabilitate, Operate, Maintain and Transfer (ROMT) contracts ·
Sale of whole or part of the assets ·
Partial or full divestiture of the Undertaking 23.
New Assets: Depending on the nature of the project, the
contractual structures/ agreements used for new projects would include, inter-alia: ·
Build & Transfer (BT) ·
Build-Lease-Transfer (BLT) ·
Build-Transfer-Operate (BTO) ·
Build-Operate-Transfer (BOT) ·
Build-Own-Operate-Transfer (BOOT) ·
Build-Own-Operate (BOO) ·
Build-Operate-Share-Transfer (BOST) ·
Build-Own-Operate-Share-Transfer (BOOST) ·
Build-Own-Lease-Transfer (BOLT) 24.
Special Purpose Vehicles: Where appropriate, GoK/ GoK Agencies may
participate in the equity structure of any SPV for the development and
implementation of infrastructure projects. The selection of the PSP for
participating in the SPV would follow the procurement process set out in
section 27. The equity structure of the SPV would be decided on
a case-to-case basis. 25.
The Infrastructure Development Corporation (Karnataka)
Limited (iDeCK) has been assisting GoK in the preparation of documents for
Infrastructure Projects, incorporating the touchstone principles set out in
this document. iDeCK would co-ordinate with the Infrastructure Development
Department (IDD) in providing assistance to concerned departments in the
preparation of sectoral strategies and action plans for the successful
implementation of projects under the ambit of PPPs. iDeCK would also assist
these departments in the project development and procurement process, where
such assistance is requested. Alternatively, these services could be procured
from independent third party consultants as may be suitably identified and
selected by the concerned project development agencies/ departments for this
purpose. 26.
GoK recognizes that creation of Infrastructure under the PPP
model requires that there be reasonable assurance that competing facilities
would not be created that would materially adversely affect the technical and
financial viability of the project. D. Procurement Process
·
Expressions of interest (EOI)/ Request for Qualifications
(RFQ) ·
Request for Proposals (RFP) -
Technical and financial proposals ·
Signing of Agreements 28.
The criteria used for selection would include objective
technical/ financial parameters, such as: ·
Level of service, quality of assets offered; ·
Lowest present value of Viability Grant support ·
Lowest quantum of land ·
Lowest present value of asset based support from the
Government; ·
Highest share (or present value of) of revenue; ·
Lowest unit value or present value of payments by GoK; ·
Highest upfront payment (or present value of upfront
payments); ·
Highest present value of future payments; ·
Lowest concession period; ·
Lowest unit value or present value of user fees; ·
Highest premium on (or present value of) equity shares
offered. 29.
A Private Sector Participant (Proposal Initiator) may submit
a suo-moto/ innovative proposal (Original Proposal) to GoK/ GoK
Agency for setting up an Infrastructure Project containing the following: ·
Articulation of the public need for the project ·
Requisite technical details, i.e., details of alignment/site,
estimates of cost, etc. ·
Cost incurred by the Proposal Initiator for the development
studies related to the project. GoK would, in
the first instance, assess the public need for the Infrastructure Project. In
case the Infrastructure Project is found to satisfy a public need, GoK would
assess the technical feasibility/ suitability of the Original Proposal and
modify the same, if required. GoK may carry out additional studies for the
project, if required. After
evaluating the proposal and considering it suitable, GoK would, put up
competitive bidding for counter proposals (“Swiss Challenge”). The Original
Proposal (except proprietary information and details of the financial proposal)
and contract principles of the Original Proposal would be made available to any
interested applicants. If the competitive bidding process results in a superior
proposal, the Proposal Initiator would be given an opportunity to match the
competing counter proposal within a stipulated time-frame, and be selected as
the project concessionaire. If the Proposal Initiator declines to match the
superior counter proposal, then the applicant that has made the superior
proposal would be selected as the concessionaire. Upon such selection, GoK/ GoK
Agency concerned shall cause/ arrange to reimburse to the Proposal Initiator, a
part or the whole of the development costs, as determined upfront and declared
in the bidding documents, and may recover the same from the successful bidder. 30.
GoK would evaluate all proposals received for any
Infrastructure Project. GoK may also choose to appoint suitable external
advisors or consultants, where necessary, for the purposes of evaluation. 31.
In order to facilitate expeditious project implementation,
GoK would endeavour to conclude the evaluation process for all Infrastructure
Projects within 90 days from the date of submission of the final proposals. In
the case of suo-moto proposals, GoK would decide to proceed with the bidding
process within 180 days of their submission. In any event,
GoK would endeavour to provide all necessary State-level clearances and enable
implementation of any Infrastructure Project being taken up through Public
Private Partnerships within 180 days from the date of submission of the final
proposals for such project. E. Regulatory Framework
32.
Given that availability of unencumbered land in a time-bound
manner is a critical pre-requisite for most Infrastructure Projects, GoK
intends to set in place suitable mechanisms, for facilitating expeditious
acquisition of land for such projects. If found necessary, GoK would also
consider promulgating a specific legislation for expeditious acquisition of
land for infrastructure projects covered under this Policy. 33.
Since many infrastructure facilities and services have
natural monopoly characteristics, independent regulation may be desirable to
ensure that the interests of both users and service providers are kept in view.
34.
GoK intends to set up independent regulatory[3]
authorities for some of the infrastructure sectors. The role of the regulator
would include setting norms for entry and exit, tariff fixation, and
establishing standards for construction, operations and maintenance for the
facilities/ services. However, the setting up of the regulatory authorities
would be decided based on the specifics of each sector. F. Institutional Framework
35.
At present the process of project identification and
development is handled by the various GoK departments and agencies and in case
of urban projects by the respective urban local bodies. The Infrastructure
Development Department (IDD) of the Government of Karnataka, which has been set
up as the nodal agency to streamline the process of appraisal and approval of
Infrastructure Projects, shall facilitate various GoK departments in developing
Infrastructure Projects through PPPs. 36.
GoK has set up a “PPP Cell” in the IDD. The PPP Cell is
headed by the Principal Secretary – IDD, and shall be adequately staffed. iDeCK
will provide technical advice and support to the PPP Cell. The PPP Cell may
also engage consultants as and when necessary. The PPP Cell will be the nodal
agency to receive the proposals in respect of the PPP projects and place them
before the SWA for consideration and approval. The PPP Cell may invite/ co-opt
representatives from the private sector, nominated by State-level Industrial
fora such as ASSOCHAM, CII, FKCCI, and KASSIA et.al. 37.
GoK shall set up a District PPP Committee at the District
level, to co-ordinate and facilitate the implementation of infrastructure
projects, including facilitation for obtaining clearances and approvals on a
PPP route. The District PPP Committee shall be chaired by the Deputy
Commissioner of the concerned district. The District PPP Committee shall have
officers of appropriate rank, nominated by the GoK, as well as upto three
representatives from the private sector, nominated by State-level Industrial
fora such as ASSOCHAM, CII, FKCCI, and KASSIA et.al. 38.
IDD would be duly strengthened with staff having appropriate
skills to enable it to co-ordinate and integrate the necessary procedures and
processes for facilitating Government/ Government Agencies in expeditious
project approval and implementation. Simultaneously, capacity would also be
built up in Government/ Government Agencies at the State and District level, to
formulate and implement Infrastructure Projects on a PPP basis. IDeCK would
support IDD and other GoK departments/ agencies in developing and financing
Infrastructure Projects on a PPP basis. The PDF and PIF administered and
managed by iDeCK, on behalf of GoK, would be utilized for this purpose, where
appropriate. 39.
A Single Window Agency (SWA) has been set up at the State
Level under the Chairmanship of the Chief Secretary to approve the projects under
PPP projects upto Rs. 50 Crores, and to recommend the projects above Rs. 50
Crores to the State High Level Committee under the Chairmanship of the Chief
Minister constituted under Section 3 of the Karnataka Industries (Facilitation)
Act 2002. In the case of all PPP proposals upto Rs. 50 Crore, the concerned
department shall, in consultation with the Infrastructure Development
Department place them before the Single Window Agency for PPP headed by the
Chief Secretary for approval. For all proposals in excess of Rs. 50 Crores, the
Single Window Agency for PPP will scrutinize the proposals and make its
recommendations to the High Level Committee, headed by the Chief Minister, for
approval. The IDD, as the nodal department for PPP, with support from iDeCK, shall
assist the concerned departments in the evaluation of all such projects. The
IDD shall also assist the Single Window Agency for PPP and HLC in evaluating
and deciding upon specific proposals. 40.
IDD would set out the process for scrutinizing and clearing
all investment proposals, frame guidelines for assessing the feasibility of
private investment, set in place standard procurement documents and framework
agreements, and assist the Government/ Government Agencies in the procurement
of developers. IDD would also facilitate the Government/ Government Agencies,
to develop and implement Infrastructure Projects in the PPP format, in an
expeditious manner. 41.
In order to facilitate financing of project development and
implementation in an efficient, sustainable and expeditious manner, GoK would
use its “Infrastructure Initiative Fund.” IDD would set out the policy and
regulatory guidelines and provide the necessary institutional support for
operations and management of the Fund. All fees and charges[4] accruing from
project development and investment initiatives of IDD/ concerned Government/
Government Agency, would be credited to the Infrastructure Initiative Fund. GoK
would also make contributions to the Fund through budgetary provisions and/or
other sources, from time to time, as it may deem appropriate. 42.
Based on the strategy developed for each sector, IDD, in
consultation with GoK Departments/ Agencies, would prepare a road map for
infrastructure development in the State that will: ·
Identify critical projects in different sectors that need
immediate attention; ·
Identify projects where significant benefits of network
extension can be exploited for integrated infrastructure development; ·
Explore the scope for PPPs in developing new Infrastructure
Projects and augmenting existing infrastructure facilities and encourage such
participation through appropriate incentives; ·
Prepare a shelf of developed projects for posing on a PPP
format; ·
Mobilize resources through appropriate policy measures to
supplement private sector investment, especially in the case of commercially
non-viable projects; ·
Identify and resolve bottlenecks in the institutional
framework that are likely to impede investments and therefore provide a
conducive environment for infrastructure development through PSP; ·
Facilitate the conversion of approved projects into the
implementation phase. 43.
The institutional roles and responsibilities are set out in
Schedule II. 44.
GoK also recognizes the role of public opinion and
stakeholder participation in facilitating Infrastructure Project development
and implementation. Since the viability of projects is contingent upon cost to
the final user, it is important to ascertain “what the market can bear”.
Mobilizing public opinion and ensuring stakeholder participation is thus an
integral part of Infrastructure Projects. IDD would collaborate with
professional bodies, NGOs, Industry Associations, and User Groups in
facilitating this process. G. Incentives and Concessions
45.
GoK would provide the incentives and concessions set out in
Schedule III to promote private finance initiatives in infrastructure
development. These would be available to all projects falling in the ambit of
Para 13
of this Policy. Investors would be eligible for any other additional incentives
and/or concessions proposed/available for projects under existing sectoral
policies/ proposed sector-specific strategies, but GoK shall take a holistic
view of the totality of incentives and concessions, vis-à-vis the viability requirements
of the project. In addition, several of these projects would also enjoy tax
benefits under the Income Tax Act, 1961, as delineated by the Government of
India. 46.
In case of projects where no private investments in the form
of private equity participation are envisaged, and where the government agency
or implementing authority directly awards the project to a contractor following
a standard procurement process, but not under a specific concession structure
as described in Para 22
- 24
of this document, no incentives and concessions would be available under this
Policy. 47.
To enhance commercial viability of projects, GoK may allow,
wherever necessary, the Concessionaire/ SPV to develop utilitarian services or
other socially acceptable commercial activities such as development of
hotels/motels, gas stations, or recreational centres etc., on the
Infrastructure Project site. 48.
Subsidies in the Infrastructure sector would be based on the
need for balancing adequate cost recovery, with social needs and regional
development. Wherever subsidy is necessitated for social/ regional needs, it
shall be the endeavour of the government to ensure that such subsidies are
direct and transparent. In all other cases, it shall be the endeavour to price
services to be commensurate with the real costs of service provision, and
sustainability of the project. 49.
To the extent that the project parameters may permit, every
project shall endeavour to maximise employment opportunities to the local
population of the State of Karnataka. V Duration and Review of Policy
50.
This policy would come into force with effect from the date
of issue of Government Order and would be effective till the formulation of a
new infrastructure policy. 51.
There would be a mid-term review of this Policy based on a
critical assessment of feedback from stakeholders, and changes in scope that
are deemed necessary and desirable, would be incorporated at that stage.
52.
The government recognizes that expanding and
institutionalising the scope of PPP in provision of infrastructure may also
necessitate appropriate changes in the existing legislative framework. It is
however felt that the present framework offers sufficient scope for PPPs in provision
of Infrastructure. The specific legislative constraints for PPPs would also be
reviewed and addressed during the mid-term review. VI Sectoral Strategies
53.
The broad principles set out in this document would govern
the various strategies to be developed for each sector. The concerned
administrative departments would finalize the sector strategies and action
plans thereunder within six months of the date this Policy comes into force. 54.
As regards the power sector, the recent policies announced by
GoK with respect to privatisation[5]
and restructuring and the Electricity Act 2003 would, inter-alia, provide the underlying basis for implementation of the
proposed sector development strategy. 55.
IDD would assist Government/ Government Agencies in making a
concerted effort to set out an action plan for already identified project
development opportunities in various infrastructure sectors in the immediate
term. IDD would use the services of iDeCK, which has been assisting several of
these departments on various projects and policies in the past, particularly in
the PPP domain, to provide the necessary project development and implementation
support. For this purpose, IDD would interface with other departments
concerned, such as the Public Works Department, Urban Development Department,
Energy Department, Commerce & Industries Department, and Department of
Information, Tourism & Youth Services, among others, to advise on and
co-ordinate identified and new project development activities. SCHEDULE
I ‑ Evaluation of Risks & Risk Mitigation Measures
Projects are subject to
various types of risks during the development, construction and operations
periods. In a PPP framework, these risks are typically assigned to parties best
able to handle them. The table below sets out the typical project risks
envisaged during the project life-cycle and their mitigation measures in a
standard Concession (BOT) contract.
SCHEDULE
II ‑ Institutional Roles & Responsibilities
SCHEDULE III ‑ Incentives & Concessions
The project would be
allowed to charge user fees (tolls, port dues etc.) during the concession
period. Recognising the fact that
infrastructure projects require special consideration in view of long gestation
periods, low rates of return and higher risks, incentives and support such as
tax holidays, tax exemptions, Viability Gap Fund, etc., have been provided
under the purview of the GoI. Apart from the
incentives, concession and support available to the projects, the GoK proposes
to offer the following incentives: A.
Facilitation v Where it is
not possible for private investors to obtain land required for the project on
their own, the Government would acquire the land required for the project; v Facilitation
in obtaining clearances and approvals from various agencies; v Facilitate in
obtaining water and power required for the project. B.
Asset-based support v Government
land may be provided, subject to availability, at concessional rates; v Wherever an
Infrastructure Project by itself is not financially viable, the private
investor may be allowed to acquire additional land on the same terms as the
land for the main project, and develop suitable commercial activities to ensure
a reasonable composite internal rate of return. Such development rights would
be consistent with applicable law and land-use, and would include commercial
complexes, hotels, housing complexes, and advertisement hoardings. Where
permitted under local regulations, this would include relaxation in the
applicable Floor-Space Index norms; v Develop
linkage infrastructure, for projects that need such critical linkages. C.
Foregoing Revenue Streams v Exemption from
entry tax and special entry tax arising in the construction of the
Infrastructure Project facility for a period of three years or till the date of
completion of the project, whichever is earlier. Only machinery, equipments,
and construction material would be eligible for this exemption. Further, the
limit of exemption would be Rs. 25 Lakhs for machinery and equipment, and Rs. 1
lakh for construction material, or as officially notified by GoK from time to
time. Such exemption would be applicable both to the developer of the
infrastructure project, or any Person authorized to execute works in the
infrastructure project; v Concession on
stamp duty on transfer of land[6]:
i.
Zone 1: 100%
ii.
Zone 2: 50%
iii.
Zone 3: Nil v Concession on
conversion fine on land:
i.
Zone 1: 100%
ii.
Zone 2: 50%
iii.
Zone 3: Nil D.
Contingent Guarantees v In specific
cases, guaranteed payment structures such as “Take-or-pay” (wherein there is an
assurance of payment for the availability of a service) or “supply-or-pay”
(wherein there is an assurance of payment for the non-availability of a
service) would be considered. E.
Financial Support v Viability gap
finance from the Central Government: The Government of Karnataka would sponsor
the project for release of Viability Gap Fund, from the Government of India v The Government
of Karnataka would also provide additional Viability Gap Fund, over the VGF of
the Central Government v Provided that
the quantum of total Viability Gap Fund shall be determined after clearly and
explicitly calculating all project costs and incentives/ concessions:
i.
Taking into account all costs of the projects, excluding cost
of land, and land related charges such as Stamp Duty & Conversion Fine
ii.
Taking into account all other incentives granted, including
asset based support and the foregoing of revenue streams, and including any
other financial incentive granted under any other sector policy, or scheme of
the Central Government, Central Government Agency, Government or Government Agency. [1] As per Guidelines on Support to Public Private Partnerships in Infrastructure issued by the Ministry of Finance, Department of Economic Affairs, Government of India [2] In line with the
report of the Dr Nanjundappa Committee on addressing regional imbalances [3] also multi-utility regulators [4] such as project development fees, application / tender charges, concession payments, interest charges, guarantee payments, taxes, cesses etc. [5] Detailed Policy Statement on Karnataka Power Sector Restructuring and Privatisation Programme; Independent Power Producers Policy [6] The Zones in this
Policy shall be identical to that defined in the Industrial Policy (2006) of
the Government of Karnataka |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||